Korte & Luitjohan Contractors, Inc., self-performed most of the critical aspects of this 300 sq ft slab-on-grade addition and 7,000 sq ft remodel of existing office and operatories. Work included site grading, water and sewer system installation, excavation of building site, foundation installation, rough framing of the building, metal studs and drywall, ceiling, installation of doors and other finishes throughout the building.
K&L worked closely with the owner to coordinate work around patient care to avoid interruptions in appointments. For example, the entire electrical service system was replaced during a 30-minute lunch break.
Due to the careful scheduling and coordination of K&L, what was originally considered to be an 8-month project, was completed in 5 months with no disruption in patient care.